Redland City Council Cleveland Library Chiller Replacement

A busy public library and council office can’t exactly press pause for major mechanical upgrades – so our team made sure they didn’t have to.

We recently completed a chiller replacement project at Cleveland Library and Redland City Council offices, removing and replacing two chiller systems, four pumps, a new Mechanical Services Switchboard (MSSB) and the building’s management system.

As part of CV’s integrated asset maintenance capability, the team carefully planned every step to keep the site fully operational. A temporary chiller was set up in the ground-level car park, allowing us to carry out the full change-over while maintaining uninterrupted air conditioning for visitors and staff.

Well done to the team – their planning, coordination and problem-solving were key to adapting the works to suit a busy community facility.