Project Overview
The University of Queensland’s Gatton Campus underwent an infrastructure upgrade to support continued campus development and increased renewable energy generation. Working alongside McNab, CV upgraded the campus electrical connection from 11kV to 33kV and established a new 33/11kV substation incorporating a 5/8 MVA transformer, 33kV switchgear and associated electrical infrastructure. The upgrade provided additional capacity for forecast electrical demand and renewable energy generation, supporting UQ Gatton’s longer-term vision of becoming an energy-neutral campus.
- Industry Schools, Universities & Technical Institutes
- Client McNab
- Location Gatton, QLD