Tantivy Pump Station – EI&C Infrastructure Upgrade
Project Overview
The Tantivy Street Pump Station upgrade is a significant infrastructure enhancement for Brisbane’s wastewater network. Delivered in partnership with Downer, the project focused on the complete overhaul and modernisation of the station’s electrical, instrumentation and control systems to ensure long-term reliability, seamless integration with SCADA systems and full compliance with Urban Utilities’ technical standards.
- Client Queensland Urban Utilities
- Location Greater Brisbane Region, QLD
Scope of Works
The project’s primary goal was to deliver a fully functional, modern sewer pump station with resilient EI&C systems, while safely decommissioning the legacy infrastructure.
Key deliverables:
- Supply, installation, testing and commissioning of new main switch board, MCC and VSD panel.
- Field installation: pump cabling disconnection boxes, remote switching panels, metering systems.